Asbestos - Air Quality(Demolition / Renovation Notification Form)What is the Purpose of this Permit?If asbestos abatement or demolition is to occur, the form must be postmarked or received at least 10 working days prior to the commencement of removal activities. The 10 working day notification period starts on the postmark date or when received by Ecology.
Who issues this Permit?Department of Ecology What Activities Require this Permit?You must submit an asbestos demolition/renovation notification form any time you:
This form must be filled out if it meets the above criteria and meets the definition of a facility. Facility means any institutional, commercial, public, industrial, or residential structure, installation, or building (including any structure, installation, or building containing condominiums or individual dwelling units operated as a residential cooperative, but excluding residential buildings having four or fewer dwelling units); any ship; and any active or inactive waste disposal site. Any structure, installation or building that was previously subject to this subpart is not excluded, regardless of its current use or function. Before beginning any work on the facility, you must:
Guidance is available on the EPA Region 10 asbestos web page and at the other links listed below. How Much Will this Permit Cost?Nothing - Ecology does not charge a fee for this notification. Where Can I Get the Application for this Permit?The application which is called 'Asbestos Demolition / Renovation Notification Form', is online and can be downloaded at http://www.ecy.wa.gov/biblio/ecy07087.html. Do I Need to Include Anything with my Application?The form must be signed by the owner/operator of the facility and mailed to the appropriate Ecology office. Is the Decision on my Permit Dependent on Anything Besides the Information in my Application?The notification must be postmarked 10 working days before the job's start date to allow Ecology to comment and/or schedule a site visit.
How Long Will it Take to Review my Application?There is no review time, only a 10 working day advance notice requirement.Where do I Submit my Application?The application submittal locations are listed on the form. Asbestos NESHAP notifications are always submitted to the appropriate Local Air Agency. If the Ecology Regional Office is acting as the local air agency (as in most of eastern Washington outside of Spokane, Yakima, and Benton County) it is submitted to the Ecology regional office. Ecology's Industrial Section receives notices from their regulated businesses. How Long is my Permit Valid?The job must be started and completed within the dates specified in the notice. If job schedules change, a change notice is required to be submitted. What is the Appeal Process for the Permit?No. Since there is no decision, an appeal is not applicable. Legal Authority:Links:
Statewide Contact:Air Quality Program Headquarters 300 Desmond Drive PO Box 47600 Olympia, WA 98504-7600 Telephone: (360) 407-6800 Fax: (360) 407-7534 Website: http://www.ecy.wa.gov/programs/air/airhome.html * Permit information last updated 10/30/2009. |
||||
![]() |
||||
|